Captive power and BERC licensing for energy-intensive plants
Why large manufacturers self-generate, what a captive power plant licence file contains, and how the approval interacts with gas, fire and environmental clearances.
Energy · 6 min read · Updated August 2026
For composite textile mills, spinning units and continuous-process plants, grid interruption is not an inconvenience but a scrap-generating event. Captive generation is the standard answer, and above a defined capacity threshold it requires a generation licence from the Bangladesh Energy Regulatory Commission alongside approval under the captive power policy framework.
What the licence file contains
- Single line diagram of the generation and distribution scheme, sealed by a qualified engineer.
- Grounding and protection design, including earthing calculations.
- Generator specifications, capacity and fuel arrangement, with the gas or fuel supply arrangement evidenced.
- Fire Service and Civil Defence clearance for the generator hall and fuel storage.
- Environmental clearance covering emissions and noise from the generation set.
- Company, project registration and land documents.
Sequencing with the gas file
A gas-fired captive plant creates a dependency loop: the generation approval expects a fuel arrangement, while the gas connection expects a defined load. The resolution is to run both files in parallel with consistent load figures and a documented supply intention, rather than waiting for one to complete before opening the other. Getting this wrong adds a quarter to the commissioning schedule.