Factory & industrial licensing

A plant is legal only when the last approval lands

Industrial licensing is a dependency graph, not a checklist. Environmental category dictates the fire file; land records dictate the utility connection; the factory licence cannot close while an inspectorate file is open.

The programme

Phases we run for a greenfield facility

Each phase has its own authority, its own document set and its own failure mode. We keep them moving in parallel wherever the law allows it.

  1. 01

    Phase 1 — Legal entity formation

    Indicative 2–5 weeks

    RJSC · NBR · City Corporation

    Establishing a Bangladeshi legal person capable of holding licences, leases, bank accounts and employment contracts.

    • Name clearance from the Registrar of Joint Stock Companies (RJSC)
    • Drafting Memorandum and Articles of Association tailored to the intended objects
    • Company incorporation and issue of the Certificate of Incorporation
    • E-TIN registration with the National Board of Revenue
    • Trade licence from the local City Corporation or Union Parishad
    • VAT / BIN registration and, where importing or exporting, IRC and ERC
  2. 02

    Phase 2 — Project registration

    Indicative 2–6 weeks

    BIDA · BEZA · BEPZA · Hi-Tech Park Authority

    Registering the investment project with the authority that governs the chosen location, unlocking work permits and incentives.

    • Selecting the correct authority: BIDA for the general domestic territory, BEZA for economic zones, BEPZA for export processing zones
    • Filing the project profile, investment schedule and machinery list
    • Payment of registration fees (indicative range, scaled to project value)
    • Obtaining the registration letter used downstream for visas, work permits and utility applications
    • Where applicable, applying through the One-Stop Service (OSS) portal of the authority
  3. 03

    Phase 3 — Operational and safety clearances

    Indicative 2–8 months depending on environmental category

    FSCD · DOE · DIFE

    The compliance core. Sequencing matters: layout approval and fire clearance are usually prerequisites to the factory licence.

    • Approved factory layout plan and building/structural approval
    • Fire licence from the Fire Service and Civil Defence (FSCD)
    • Environmental Clearance Certificate (ECC) from the Department of Environment, preceded by IEE or EIA where the category demands it
    • Factory licence from the Department of Inspection for Factories and Establishments (DIFE) via the LIMA portal
    • Group insurance, workplace safety committee and statutory registers
  4. 04

    Phase 4 — Utilities and specialised licensing

    Indicative 2–9 months, largely dependent on utility availability

    Titas · REB/BREB · BERC · Boiler Directorate · Explosives · BRTA

    Energising and specialising the plant. These files run in parallel and are the most common source of schedule slippage.

    • Industrial gas connection application with layout, GIS location and load calculation
    • Electricity connection via DESCO/DPDC or the local Palli Bidyut Samity, including feasibility study and wiring inspection
    • Captive power plant approval and BERC licence where self-generation exceeds the licensing threshold
    • Boiler registration and inspection under the applicable Boiler Rules
    • Explosive, acid and chemical storage licences where hazardous materials are held
    • BRTA registration for company vehicles and covered vans

Reference tables

Indicative classifications, sequences and timelines

Published as ranges to help you plan. Confirm the current official position with the authority before committing a schedule or a budget.

Environmental categories and clearance route

The Department of Environment classifies projects by pollution potential. The category dictates the study required and the realistic timeline.

CategoryTypical industriesStudy requiredIndicative clearance timeline
GreenAssembly, tailoring, light servicesNone beyond application3–8 weeks
Orange-ASmall food processing, printingBasic documentation and site plan1–3 months
Orange-BGarments with washing/dyeing, plasticsInitial Environmental Examination (IEE)2–5 months
RedChemicals, tanneries, power, cementFull Environmental Impact Assessment (EIA)4–8 months or longer
Indicative figures only — verify current official rates with the relevant authority before budgeting. Reviewed August 2026.

DIFE factory licence — establishment classes

Establishment class is set by worker headcount and determines the licence fee band and renewal scrutiny. Fee bands below are indicative and must be confirmed against the current gazette.

ClassIndicative worker bandIndicative fee band (BDT)Typical profile
BUp to ~50 workersLowest band — low thousandsSmall assembly or packaging unit
C~51–100 workersLow bandLight manufacturing
D~101–500 workersMid bandMid-size garment or engineering plant
E~501–1,000 workersUpper-mid bandLarge manufacturing unit
HSeveral thousand workersHighest band — tens of thousandsComposite mill or industrial park tenant
Indicative figures only — verify current official rates with the relevant authority before budgeting. Reviewed August 2026.

Utility connection — sequence and duration

Utility files are the most common cause of commissioning delay because they depend on network availability, not only on your paperwork.

StepGas (Titas / regional)Electricity (PBS / DPDC / DESCO)
Application and load declarationLayout, GIS location, load calculationFeasibility application with connected load
Technical assessmentNetwork availability and pressure surveyFeasibility study and line route survey
Cost settlementDemand note and security depositConstruction cost deposit
Installation and inspectionPipeline, station and meter installationWiring inspection by licensed electrician
EnergisationIndicative 3–9 months overallIndicative 6–16 weeks after deposit
Indicative figures only — verify current official rates with the relevant authority before budgeting. Reviewed August 2026.

Land mutation (namjari) — realistic durations

Mutation updates the government record to your name. The statutory target and the practical duration differ; disputes extend both.

Case typeIndicative durationPrincipal risk
Clean title, undisputed transfer1.5–3 monthsIncomplete via-deed chain
Inherited or partitioned land3–6 monthsMissing heirs or unregistered partition
Disputed or court-involved6–18 months or longerInjunction and appeal cycles
Land converted from agricultural useAdd 1–3 monthsLand-use conversion approval
Indicative figures only — verify current official rates with the relevant authority before budgeting. Reviewed August 2026.

Talk to us

Planning a plant?

Share the sector, the site and the intended production date. We will return a sequencing view showing what must start now.